Formwork for stairs 11.08.02
Add to my wish listFor the construction of your balanced stairway formwork, nothing is simpler than using telescopic tubes. These adapt perfectly to the length required and avoid long and cumbersome bevel cutting wood. The formwork of a balanced stairway becomes child's play and a very fast operation.
Once the tubes have been placed, just cover them with a reinforced bubble mat, and place your reinforcements and risers before concreting.
For a stairs with 16 steps of 1 m wide, you need:
- About 2 hours' work
- 90 tubes 92-160 and 10 146-200
A ceiling is required in the lower part